Tunnel bypass Flüelen, Switzerland
Info projecten
Ligging: Flüelen, Zwitserland
Oval-shaped tunnel cross-section with a height of 12.80 m
- total length: 2.6 km
- construction period: 1999 - 2005
Vereisten
- section-wise concreting of the complete cross-section in one pour
- short construction time
Klant
Arge Tunnel Umfahrung Flüelen (ARGE TUF) Murer AG, Erstfeld -
Prader AG Tunnelbau, Zürich; Zschokke Locher AG, Zürich; Rothpletz Lienhard + Cie AG, Aarau; CSC Impresa Costruzioni SA, Lugano
Voordeel klant
- four tunnel sections finished in only 9 days
Felix Bissig | Hansruedi Walker
Foremen
From PERI, we got the most efficient solution. Despite the large dimensions, we were able to concrete in one pour!
PERI oplossing
- tunnel formwork carriage for four sections with section lengths of 5.50 m
- since there were only four cycles, decision to go without integrated hydraulics
PERI systemen ter plaatse