Motorway Bridge D1, Slovakia
Info projecten
Ligging: Považská Bystrica, Slowakije
The “Centrum” motorway junction as a 767-metre-long bridge structure
Construction period: 2008 - 2010
Vereisten
- single and twin-spaced hollow box cross-sections with variable superstructure widths
- the cross-sections as well as the longitudinal and lateral inclinations change continuously
Klant
Bögl a Krýsl, k.s, Prešov
Voordeel klant
- cost-effective construction using rentable system components from the VARIOKIT system
- transfer of vertical and horizontal loads from a height of over 15 m
- bundling of standards for concentrated load points using PERI UP Flex falsework
Ľuboš Šalváry
Site Manager
We have been working together with PERI for many years now, and once again we have not been disappointed. For each bridge section, we received the right formwork and scaffolding solution.
PERI oplossing
Planning and execution based on rentable modular systems:
- construction of the hollow box cross-sections for the superstructure was effected with 15-m-high PERI UP falsework
- the external web formwork and cantilever formwork were created by means of variable raised formwork units using VARIOKIT system components
PERI systemen ter plaatse